Project of the month . January 2019

Austria Campus

Austria Campus is a business site with a total area of 200,000 m² consisting of all in all six office blocks. The Campus is part of the Nordbahn quarter created on the area of the former northern railway station and one of the biggest structural engineering projects currently realized in Europe.

FCP first carried out a TDD (Technical Due Diligence) in the course of transaction for the construction sites 5, 8 and 6 and subsequently the building project was supported in the scope of a construction monitoring order. After the conclusion of monitoring, FCP has still been involved in technical consulting.

The construction sites 5 and 8 have already been completed and Bank Austria has moved in. The construction site BF6.1 was also completed and put into operation by the hotel operator ‚Äúrooms‚ÄĚ. The construction sites BF6.2 and BF6.3 are currently in the completion phase.

Client . AOC Immobilien

Services . TDD and construction monitoring